Main Office & New Front Entrance - Completed with only final touches to be added, including permanent carpet installation. The new main entrance stairs and ramp are also complete; the new canopy is also expected to be finished soon.
Demolition was completed before students arrived; exterior work will continue, as scheduled, through the fall and winter with anticipated completion in late spring 2018.
Hard barriers in place between construction and corridors. Locked doors, hard barrier, plastic seal.
Demolition was completed before students arrived; exterior work will continue, as scheduled, through the fall and winter with anticipated completion in late spring 2018.
Hard barriers in place between construction and Gym and Old Multi-purpose room . Hard barrier, plastic seal in gym. Plastic covering, brick wall, hard barrier, plastic seal on old Multi-purpose room.
A new playground was installed as part of a plant improvement project in the 2017-18 budget.
Completed on time for student arrival.
Completed on time for student arrival.
Work continues in this area. Scheduled to be completed in late November.
Close to completion, but unable to be occupied until completion of the Learning Commons enables access.
Now opened for student use. All major equipment installed and the Center has been cleaned and is safe for occupancy.
Completed and open.
Work continues in these areas. Due to the courtyard’s location in an enclosed area, surrounded by classrooms, work will only occur during non-student hours. We are awaiting an updated schedule based on these shortened work hours; we don’t anticipate this complex project to be finished before the new year.